Not much to report with building over the past week. The house spent several days drying out (only to have more rain scheduled for today!). Yesterday Jamie & his crew came back and finished up some leftover work. They finished foaming & taping all of the panel seams. They also framed in the door for the pantry they got forgotten earlier in the project. They also fixed a major "Oops" that Emily discovered over the weekend. There was a window in the wrong place! The CAD drafter for Extreme Panel created the panel drawings from an old set of house plans! Not sure how that happened because we finalized our house plans way back in March. As you can see in the photo below, the window has off by ~2 feet. Fortunately, they were able to move it over by cutting a new hole in the panel & placing the cut out portion of the panel in the previous window opening.