September 18, 2013

Day 42 The View From Above (and Below!)

This will be the view out our bedroom window



Starting to frame the bearing walls for the 2nd floor


A bit more rain fell this morning with more on the way tomorrow.  Fortunately, things are still progressing.  Jamie & his crew finished all of the walls today.  Tomorrow (if weather permits) they will lay the floor trusses over the garage & start on the bonus room above the garage.


Meanwhile, Nick from Hoffman Plumbing finished with all the rough in plumbing for the basement, and Ron laid down the insulation for the basement floor. We decided to use 4 inches of foam insulation under the floor instead of the standard 2 inches.  I'm also a friend of the Sauk River Watershed District once again thanks to getting the "erosion control" fence put up.  Sarah from the city planning office sent me a friendly reminder on that one!
Erosion fence up?  Check!